GELSPRAIN UPDATE--major work on Ardsley Road to be completed by next Wed--LEAF/DEBRIS UPDATE..
Release Date: December 12, 2011

Many residents have expressed concern about the traffic jams on Ardsley Road--due to construction at Gelsprain. Good news. The work should be completed by Wednesday of next week. Toll BROTHERS is providing a bi weekly construction schedule to the town which we are posting on the website for people who are following construction.
 

DEBRIS/LEAF PICKUP UPDATE-- We are making progress re: leaf/debris pickup. But---it's very slow. The branches are heavy. And--leaves/branches are picked up separately. We still have substantial areas that have not had pickup. We have 3-4 crews working every day. For example, today a crew that we had hoped to assign to debris/leaf pickup is working removing a dangerous tree.
 

THE PLAN---EVEN THOUGH I HATE THE WORD OVERTIME, WE NEED TO TRY TO CLEAR AS MUCH OF THE DEBRIS AS POSSIBLE BEFORE THE FIRST SNOW STORM. I SUGGESTED THAT OUR CREWS WORK LONGER HOURS DURING THE WEEK AND THIS SATURDAY. WE'RE WORKING AS HARD AS WE CAN. PAUL FEINER
 
-----Original Message-----

From: Jeff Schiller

Sent: Monday, December 12, 2011 9:19 AM

To: Paul Feiner; John Lucido; Thomas Madden; Joseph DeCarlo

Cc: Christopher Badger; James Fitzpatrick; Mike Nice

Subject: FW: how much longer will ardsley road be a mess...

 

Dear Mr. Feiner,

 

Initial work on Ardsley road should be completed by Wednesday of next week if not sooner. Please note that additional work on Ardsley Road is required however we anticipate conducting that work in the spring. 

 

Toll Brothers will be providing a bi-weekly construction schedule to the Town which they will post on their website. 

We have been working with Mike Lepre on this with our last update submitted on 12/9, a copy is shown below:

 

12/2/11 Toll Ardsley Chase - Construction Schedule for the next 2 weeks (subject to change):

 

*             Install 8" Water main on Ardsley Road

*             Install temporary asphalt replacement sidewalk & driveway aprons

*             Install temporary stone access road Phase 1

*             Repair pothole created by Con Edison (if they do not address it first)

*             Install silt fence and begin processing stumps from previous Phase 2 clearing limits

*             Construct concrete slab for water booster station

*             Install 10" Tapping Valve and 10" Water Main work on Ardsley Road (dependent on tapping sleeve delivery)

*             Crane and delivery of Booster Station Scheduled for (12/15).

*             Detention Pond #2 slope/stone wall construction

 

Please let me know if you have any further questions.

Thank you,

Jeff

 

Jefferson W. Schiller, PE

Land Development Manager

Toll Brothers, Inc.

-----Original Message-----

From: Paul Feiner [mailto:pfeiner@greenburghny.com]

Sent: Sunday, December 11, 2011 11:36 PM

To: Christopher Badger

Cc: Joseph DeCarlo; Thomas Madden; John Lucido

Subject: how much longer will ardsley road be a mess...

 

chris/Chief/Thomas/John: I'm getting alot of angry calls from residents of ardsley and sprain road about the daily traffic jams on Ardsley Road. How much longer will this last? PAUL FEINER

****************************************************

Visit our web site at www.greenburghny.com and view archived Supervisors Reports.

****************************************************