UPDATES--CON ED GAS LEAK REPAIRS (RIDGE ROAD, CENTRAL AVE, HARTSDALE)... COMPREHENSIVE PLAN HEARING
Release Date: June 03, 2016

COMPREHENSIVE PLAN HEARING WED----HEARING WILL NOT BE CLOSED ON WED

The Greenburgh Town Board will hold a public hearing on the proposed Comprehensive Plan Wednesday night at 7:30 PM but we will not close the hearing Wednesday. If residents need more time to review the plan they will have other opportunities to appear before the Town Board to highlight their views.

 

CON ED GAS LEAK UPDATES....RIDGE ROAD AND CENTRAL AV

I received the following e mails from the manager of Public Affairs for Con Ed about the Ridge Road and Central Ave gas leak restoration projects.

 

The project at Ridge Road is expected to be completed within the next 2-3 weeks, then we will schedule the restoration.

 

 

Central & Hartsdale is an ongoing gas main replacement project.

 

 

CENTRAL AVE/WEST HARTSDALE AVE GAS LEAK UPDATE

 

 

Here is an approximate timeline on the main replacement. As I had mentioned earlier, we hit rock during construction which has extended the project timeline.

 

June – continue installation of new gas main

July  - gas department activates the new main, backfills & temp patch restoration

August – restoration to the roadway

 

Thank You

 

Orlando Alves

Public Affairs Manager

 

ETHICS LAWS

I was invited by Assemblywoman Sandra Galef to speak at an event in NYC today about the Greenburgh Ethics laws--considered by many to be the strongest ethics laws in NYS, if not the nation. Elected officials are prohibited from accepting campaign contributions from developers, applicants, attorneys representing developers, consultants, contractors who work for the town and town employees. We're pushing for stronger ethics laws in NYS. If you need my help today I won't be in the office much of the day. Can be reached at 989 1545 or via e mail: pfeiner@greenburghny.com.

PAUL FEINER