Traffic Advisory/Bronx River Parkway
Release Date: July 22, 2002

RESURFACING AND RELATED SAFETY IMPROVEMENTS
BRONX RIVER PARKWAY
CITIES OF YONKERS AND WHITE PLAINS,
TOWNS OF EASTCHESTER AND GREENBURGH,
AND VILLAGE OF SCARSDALE
FROM HARNEY ROAD TO RIVER ROAD AND
FROM MAIN STREET TO CEMETERY ROAD
A DISTANCE OF 3.2 MILES
AND DECK REHABILITATION OF CRANE ROAD BRIDGE
CONTRACT NO. 00-569

FUNDED THROUGH COUNTY'S CAPITAL IMPROVEMENT PROGRAM.
WORK INCLUDES MILLING AND ASPHALT PAVING.
INSTALLATION OF 8,000 LF OF RUSTIC BOX BEAM GUIDE RAIL.
REPLACEMENT OF 2,000 LF OF GALVANIZED RAIL WITH RUSTIC RAIL.
REMOVAL OF 62 TREES OUTSIDE SAFETY CLEAR ZONE.
INSTALLATION OF 62 TREES OUTSIDE SAFETY CLEAR ZONE.
REMOVAL AND REPLACEMENT OF CONCRETE MEDIAN BARRIER AND CLARE SHIELD ACROSS CRANE ROAD BRIDGE.
REPAIR OF JOINT AND WATERPROOFING DECK OF CRANE ROAD BRIDGE.
INSTALLATION OF RAISED REFLECTORIZED PAVEMENT MARKINGS, PAVEMENT STRIPING, TRAFFIC SIGNAL LOOPS.
APPROXIMATE DURATION OF PROJECT, 6 MONTHS (EXCLUDING WINTER SHUTDOWN).
MILLING AND PAVING THROUGH GARTH WOODS TO BE PERFORMED AT NIGHT, 10:00 PM TO 6:00 AM-(3 NIGHTS NORTHBOUND LANES, 3 NIGHTS SOUGHBOUND LANES). ALTERNATELY NORTHBOUND AND SOUTHBOUND TRAFFIC TO BE DETOURED ALONG POPHAM ROAD AND EAST PARKWAY TO CRANE ROAD ENTRANCE/EXIT IN SCARSDALE.
 SINGLE LANE DETOUR NB AND SB ACROSS CRANE ROAD BRIDGE DURING BRIDGE REHABILITATION AND CLOSURE OF PIPELINE ROAD ENTRANCE ONTO SOUTHBOUND PARKWAY (4 MONTHS).
PROJECT COST $2,300,000 ROADWORK, $700,000 BRIDGE WORK.
PROJECTED ADVERTISEMENT LATE JULY 2002.
ANTICIPATED CONSTRUCTION START DATE OCTOBER 2002.
PHASE 1 HARNEY ROAD TO CRANE ROAD, OCT-NOV 2002.
PHASE 2 & 3 crane ROAD TO CEMETERY ROAD, SPRING 2003.
CRANE ROAD BRIDGE, SPRING 2003.