SPRAIN ROAD, FORT HILL ROAD PAVING SCHEDULES--WORK TO BEGIN TOMORROW--SOME TRAFFIC IMPACTS
Release Date: May 10, 2018

 

SPRAIN ROAD, FORT HILL ROAD, PAVING SCHEDULES—WORK TO BEGIN TOMORROW ON SPRAIN---EXPECT TRAFFIC DELAYS

The plan is to begin milling of Sprain Road from Hidden Glen to Jackson Avenue TOMORROW, May 11th. Due to the size of Sprain Road and Fort Hill Road, it is not possible to mill and pave both within a week’s time and so one will have to be left milled over the weekend. 

May 11 – Sprain Road (Hidden Glen to Jackson) - Mill

May 14 – Sprain Road (Hidden Glen to Jackson) – Mill

May 15 – Sprain Road (Hidden Glen to Jackson)– Pave

May 16- Fort Hill Road – Mill

May 17 – Fort Hill Road – Mill

May 18 – Fort Hill Road – Pave

May 21 – Sprain Road (Ardsley to Underhill) – Mill

May 22 – Sprain Road (Ardsley to Underhill) – Mill

May 23 – Sprain Road (Ardsley to Underhill) – Pave

 

Virtual Message Boards are placed out at the Sprain Road/ Jackson Avenue intersection and at Ardsley Road advising of the upcoming work on Sprain Road. Alternating two – way traffic will be in place for this work.

 

There could be traffic delays. If you have a child who is going to the Ardsley schools please consider the above when making plans to drop off and pick up your child from school.